Planning guide
How to compare two remodeling estimates
The lowest total is not the lowest price unless the scope matches. A side-by-side method, and what New York law requires in the contract itself.
Short answer
Compare scope before price. Put both proposals side by side and check the same items: work included, materials and allowances, exclusions, permits, payment schedule, timeline and how changes are priced. In New York, a home improvement contract must also be written, signed by both parties, and include specific notices, including your right to cancel.
- Who it is for
- Homeowners in New York City and Suffolk County collecting quotes for kitchens, bathrooms, basements or whole-home work.
- What it covers
- Reading proposals and contracts side by side so the comparison is fair.
- When to read it
- After the site visits, before you sign or pay a deposit.
Step 1: give every bidder the same inputs
The same-input rule. Before the site visits, give every bidder the same written scope: the room list, any drawings, the fixture and finish list, the appliance list and, in a co-op or condo, the building's alteration agreement. Bids built from different inputs cannot be compared, however carefully you read them.
Write down every item each proposal includes, then mark where they differ. Common gaps: one estimate includes electrical work and the other excludes it; one prices custom cabinets and the other stock; one includes disposal and floor protection and the other does not.
If the scopes differ, ask both contractors to price the same list. A fair comparison is the same work, the same materials and the same assumptions.
Step 2: read and normalize the allowances
An allowance is a placeholder amount for something you have not chosen yet, such as tile, a faucet or light fixtures. A low allowance makes a proposal look cheaper but shifts the cost to later. Compare allowances item by item, and ask whether each one includes installation or only the material.
To normalize allowances:
- List each allowance in each bid: the item, the amount, and whether installation is included.
- Pick one figure per item, ideally the price of a real product you would choose, and use it for every bid.
- Add the difference to any bid whose allowance is lower, and record it as an adjustment, not a mistake.
- Where one bid includes installation and another does not, ask the second bidder to price it.
Step 3: find the exclusions and owner-supplied items
- Permits, filing fees and design professional fees
- Plumbing, gas and electrical work by licensed trades
- Repair of hidden damage found after demolition
- Demolition, disposal, dumpster and protection of floors, halls and elevators
- Painting and patching of adjoining rooms
- Appliance installation and hookups
- Lead-safe work practices in a home built before 1978
- Heating, cooling and ventilation changes: exhaust fans ducted outside, a range hood route, radiator or duct moves
- The asbestos assessment DOB requires before a permit, and any abatement
- Building or board requirements: deposits, insurance certificates, elevator bookings and work hours
Owner-supplied items. If you buy fixtures, tile or appliances yourself, each bid should say who receives and checks the deliveries, who stores them, who installs them, and who is responsible if an item arrives damaged or does not fit.
The scope lines that most often differ between bids
| Line | What to confirm in each bid |
|---|---|
| Demolition, protection and debris | What is removed, how floors, halls and elevators are protected, and who hauls debris |
| Plumbing and gas | Which fixtures move, whether old supply and drain lines in opened walls are replaced, and who files |
| Electrical | New circuits, panel work, lighting and outlets, and whether the electrical permit is included |
| Heating, cooling and ventilation | Exhaust fans ducted outside, the range hood route, radiator or duct changes |
| Permits and filings | Who files, in whose name, and whether fees and the design professional are in the price |
| Asbestos | Whether the assessment required before a DOB permit, and any abatement, are included |
| Building or board | Alteration-agreement costs: deposits, insurance certificates, work hours, elevator bookings |
| Owner-supplied items | Who receives, stores and installs them, and who replaces a damaged one |
| Project management | Who supervises the site day to day, coordinates the trades and books inspections |
| Warranty | How long, what it covers (workmanship, materials or both), what voids it, and how to make a claim |
Step 4: check the contract requirements under New York law
New York General Business Law section 771 sets requirements for written home improvement contracts. Read the statute, or ask NYC's Department of Consumer and Worker Protection (DCWP) or the Suffolk County Department of Consumer Affairs, before you sign.
Step 5: verify the license for your location
In New York City, the Department of Consumer and Worker Protection (DCWP) requires a home improvement contractor license for work costing more than $200 on a residential building. You can check a license by calling 311 or through nyc.gov/dcwp. DCWP also advises paying no more than 25% of the contract amount upfront, never paying in cash or without a contract, and notes that homeowners who use an unlicensed contractor are not eligible for its Trust Fund repayment options.
In Suffolk County, home improvement licensing is handled by Suffolk County Consumer Affairs, which offers an online search of licensed contractors.
Current lookup routes (checked 2026-11-08). These are the official routes as they appeared on that date. Pages and tools change, so start from the agency's own site rather than a saved link.
| Location of the house | Official route | What it shows / notes |
|---|---|---|
| New York City (five boroughs) | DCWP's "Check License Status" page links to its online Search Business tool; no login or account is needed to search. You can also call 311. | Whether an individual or business holds a DCWP license. For complaint history, DCWP's tips page says to call 311 and ask for a "Business Background Check". |
| Suffolk County | Suffolk County Department of Consumer Affairs online License and Complaint Violation look-up. | Search by license ID, name, business name, phone, address, city or zip code. The page notes that a search by a specific license type shows license data only, not complaint or violation data. |
- Write down the business name, the individual's name and the license ID exactly as they appear on the proposal.
- Look up the license on the route for the county where the house is, not where the contractor's office is.
- Check that the name, business name and license ID match the proposal, and note the status and the date you checked.
- Run a separate complaint search where the agency offers one (in Suffolk, search without selecting a license type; in NYC, ask 311 for a business background check).
- Ask separately for licenses that the home improvement license does not cover, such as a licensed plumber or electrician, and for the EPA lead-safe firm certification in a pre-1978 house.
- Keep a screenshot or note of each result with the proposal.
Suffolk County licenses home improvement contractors under Chapter 563 of the County Code. For what it requires, read the chapter or ask the Suffolk County Department of Consumer Affairs.
Step 6: compare how changes will be handled (change orders)
Every renovation meets something unexpected. Ask each contractor how a change will be documented, priced and approved, and whether work stops until you sign. A clear written change-order process protects both sides and keeps the final price traceable.
For how changes to a home improvement contract must be made, see GBL section 771 (Step 4). DCWP's home improvement tips page also links a sample change order form. Ask each contractor to show you the form they use, and compare what it records.
- What is being changed, described as specifically as the original scope
- Why: owner request, a hidden condition found after demolition, or a code or inspector requirement
- The price effect, shown as an amount added or credited, and whether any allowance is used up
- The effect on the schedule, if any
- Signatures and date from both sides before the changed work goes ahead
- A running log, so the final total can be traced from the contract price through every signed change
When two proposals handle changes differently (for example, one prices changes at a stated markup and the other at time and materials), note that in the comparison table. A lower base price with an unclear change process can end up harder to compare than it looks.
Step 7: check insurance and who files the permits
- Insurance: ask each contractor for a certificate of insurance, and in a co-op or condo compare it with what the building's alteration agreement requires.
- Permits: in New York City, DCWP says the contractor must make sure the appropriate party obtains the permits city law requires. Ask each bidder who files, in whose name, and whether filing fees are in the price.
- Payment schedule: line up when each payment is due against what will be finished by then, not against dates alone.
Step 8: compare schedule, supervision and warranties
Schedule. Check that the contract states start and completion dates (Step 4). Compare both bids against the same scope, and ask what happens to the dates when a board, LPC or DOB step takes longer than planned.
Who runs the job. Ask each bidder to name who supervises the site day to day, who coordinates the licensed trades, who books inspections and whom you call with a problem. A lower bid that leaves coordination to you is not the same job.
Warranties. Ask that all charges and warranties are written into the contract. Compare what each warranty covers (workmanship, materials or both), for how long, what voids it and how a claim is made, and make sure it is written into the contract.
Worked example: leveling two bids (hypothetical numbers)
Two bids for the same bathroom arrive: Bid A at $40,000 and Bid B at $46,000. Read side by side, three differences appear.
| Line | Bid A | Bid B | Adjustment to Bid A |
|---|---|---|---|
| Bid total as submitted | $40,000 | $46,000 | none |
| Tile allowance (your chosen tile is expected to cost $5,000) | $2,000 | $5,000 | +$3,000 |
| Debris removal and floor protection | Excluded | Included ($1,500 line) | +$1,500 (Bid B's line as a placeholder) |
| New exhaust fan ducted outside | Excluded | Included ($2,000 line) | +$2,000 (same placeholder) |
| Leveled total | $46,500 | $46,000 | Bid A is now $500 higher |
Once both bids price the same scope, the cheaper bid is the more expensive one. The placeholders are only a starting point: ask Bid A to price the missing work itself, and ask Bid B whether its tile allowance includes installation.
Putting it together: a comparison workflow
- Collect each proposal in writing and put it into the side-by-side table below.
- Give every bidder the same inputs (Step 1) and ask for re-pricing where the scopes still differ.
- Compare allowances and exclusions line by line (Steps 2 and 3).
- Level the bids: normalize allowances and add placeholder lines for omitted scope, as in the worked example, then ask each bidder to price its gaps.
- Check each license on the official route for the house's county and note the date (Step 5).
- Compare payment schedules and the change-order process (Steps 4 and 6).
- Compare schedules, supervision and warranties (Step 8).
- Read the contract itself against the GBL section 771 list before signing, and keep your signed copy.
- If anything about your rights is unclear, ask an attorney before signing or paying a deposit.
Planning aid
Bid-leveling worksheet (print this page, or copy the table)
| Item | Estimate A | Estimate B | Estimate C | Adjustment or note |
|---|---|---|---|---|
| Same written inputs given (scope, drawings, finish and appliance lists) | ||||
| Scope of work (rooms and tasks) | ||||
| Cabinets or fixtures: brand, line, model | ||||
| Allowances: amount, and installation included? | ||||
| Allowances normalized to one figure per item | ||||
| Owner-supplied items: who receives, stores, installs | ||||
| Demolition, protection and debris | ||||
| Plumbing, gas and electrical work by licensed trades included? | ||||
| Heating, cooling and ventilation work | ||||
| Permits and professional fees included? | ||||
| Asbestos assessment and any abatement | ||||
| Board or building requirements priced | ||||
| Exclusions listed | ||||
| Deposit and payment schedule | ||||
| Start and substantial completion dates | ||||
| Who supervises the site and books inspections | ||||
| Change-order form shown; how changes are priced | ||||
| Warranty: length, coverage, how to claim | ||||
| License and issuing agency checked; license ID matches (date checked) | ||||
| Complaint history checked | ||||
| Insurance information provided | ||||
| Leveled total (bid total plus adjustments) |
From planning to a project
Plan this with us: Kitchen remodeling by area
- Kitchen remodeling · Queens Kitchen remodeling for Queens houses and two-family homes Compact mid-century kitchens replanned for storage and counter space
- Kitchen remodeling · Brooklyn Brooklyn kitchen remodeling for rowhouses and pre-war homes Galley and through-room kitchens planned to measured aisle widths
- Kitchen remodeling · The Bronx Bronx kitchen remodeling for apartments and houses Co-op and condo kitchens planned around the alteration agreement
- Kitchen remodeling · Manhattan Kitchen remodeling for Manhattan co-ops, condos and townhouses Layouts drawn around fixed plumbing risers and the existing gas line
- Kitchen remodeling · Staten Island Kitchen remodeling for Staten Island houses Refresh or full remodel decided before design, with reasons in writing
- Kitchen remodeling · Suffolk County Kitchen remodeling for Suffolk County houses Mid-century kitchens replanned inside the existing walls
Sources
- New York General Business Law § 771: Home improvement contracts, New York State Senate (Consolidated Laws) (current text as displayed). Accessed 2026-11-02.
- Quick Tips When Hiring a Home Improvement Contractor, NYC Department of Consumer and Worker Protection. Accessed 2026-11-02.
- Licensing, Suffolk County Department of Consumer Affairs. Accessed 2026-11-02.
- Lead Renovation, Repair and Painting Program, U.S. Environmental Protection Agency. Accessed 2026-11-02.
- Check License Status, NYC Department of Consumer and Worker Protection (undated (footer (c) 2025)). Accessed 2026-11-08.
- Home Improvement Contractor License Check, NYC311 (undated (footer (c) 2026)). Accessed 2026-11-08.
- Hiring a Home Improvement Contractor Tips (re-opened), NYC Department of Consumer and Worker Protection (English PDF dated 06/2026). Accessed 2026-11-08.
- Search Licenses and Complaints, Suffolk County Department of Consumer Affairs. Accessed 2026-11-08.
- Suffolk County Law Regarding Home Improvement License (CA-L01a, Chapter 563 compilation), Suffolk County Department of Consumer Affairs (file dated 2025-05 (form code 5/25)). Accessed 2026-11-08.
- New York General Business Law § 771 (re-opened), New York State Senate (Consolidated Laws) (2021-10-29 (most recent revision shown); subsection (i) effective 2022-04-23). Accessed 2026-11-10.
- Hiring a Home Improvement Contractor, NYC Department of Consumer and Worker Protection. Accessed 2026-11-09.
- Hiring a Home Improvement Contractor (re-read), NYC Department of Consumer and Worker Protection (English tips updated 06/2026). Accessed 2026-11-10.
- Home Improvement Fact Sheet, New York State Office of the Attorney General (undated (page copyright 2026)). Accessed 2026-11-10.
- Project Requirements: Asbestos, NYC Department of Buildings. Accessed 2026-11-10.